A259 cycle route work to see 40mph limit put in place

Notice has been given that a 40mph speed limit will be in place for the A259 while the new cycle route is created.
Cycle Route
A new" shortest cycle route" from Littlehampton to Bognor Regis is to be contructed. Pictured is the proposed end of the route at the Clymping roundabout by the cricket club and looking  towards Church Lane.

Clymping ,West Sussex.

Picture: Liz Pearce 11/10/2016
LP1601085 SUS-161110-164320008Cycle Route
A new" shortest cycle route" from Littlehampton to Bognor Regis is to be contructed. Pictured is the proposed end of the route at the Clymping roundabout by the cricket club and looking  towards Church Lane.

Clymping ,West Sussex.

Picture: Liz Pearce 11/10/2016
LP1601085 SUS-161110-164320008
Cycle Route A new" shortest cycle route" from Littlehampton to Bognor Regis is to be contructed. Pictured is the proposed end of the route at the Clymping roundabout by the cricket club and looking towards Church Lane. Clymping ,West Sussex. Picture: Liz Pearce 11/10/2016 LP1601085 SUS-161110-164320008

The order, published by West Sussex County Council, states it will come into effect on Monday (July 31) and remain in force for 18 months or until the works are completed – whichever is earlier.

However a spokesman has since confirmed: “The temporary 40mph speed limit will be implemented when the construction starts in the autumn and will last for the duration of the works (expected to be completed early 2018).”Effected parishes are Felpham, Middleton-on-Sea and Climping, from the roundabout at its junction with Flansham Lane to the exisiting 40mph speed limit at Yapton Road (B2233) in Climping.

Hide Ad
Hide Ad

The announcement follows new this week that the project has been approved a budget rise of £800k.

The money is to make up the funding shortfall for the scheme, which is to provide a 4.5km length of direct pedestrian and cycle facility between the two seaside towns, is reported to have been identified as part of the ‘tender evaluation process’ last month.

A report, which formed part of the decision documents, stated: “£345,000 has been spent to date on scheme design and enabling works leaving £920,000 of uncommitted budget which is insufficient to deliver the scheme.”

It added: “In order for the scheme to be constructed it is estimated that a further £800,000 of budget will be required to create a total scheme budget of £2,065,000.”

The report also revealed that the additional budget requirement will ‘be met by re-prioritising other schemes within the portfolio.’